Pick a road to see the projects on it and every figure published about it, from every project and every document: the county’s traffic boards, FDOT’s counts, the Turnpike’s study and the county budget, side by side. Pick a second road to go straight to where the two meet. Tap any figure to see its source.
99 figures · 13 roads with figures · 36 stretches and intersections · 77 listed projects
Roads
Is about Rangeland Blvd: “By connecting the existing and planned segments of Rangeland Blvd, Bud Bexley Parkway, and Tower Road together, the corridor will serve as a regional collector that enhances connectivity to the surrounding areas.” — Corrections and clarifications to this guide, by email
Is about Bud Bexley Pkwy: “By connecting the existing and planned segments of Rangeland Blvd, Bud Bexley Parkway, and Tower Road together, the corridor will serve as a regional collector that enhances connectivity to the surrounding areas.” — Corrections and clarifications to this guide, by email
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Listed onlyUS 41/SR 54 West of Wilson Rd/SR 54 to East of Osprey Ln/ SR 54Construct grade separated interchange · FDOT · status as listed: ROW Advanced to FT27 from FY29MPO 2026 priority list, page 27, priority 1 ↗
Listed onlyStarkey Trail at SR 54 S of Starkey Blvd to N of Starkey BlvdPedestrian overpass · FDOT · status as listed: Funded with Penny for PascoMPO 2026 priority list, page 28, priority 30 ↗
Listed onlyCollier Parkway/ SR 54 Interchange Collier Parkway at SR 54New interchange · FDOT · status as listed: Project Not in 2050 SIS CFPMPO 2026 priority list, page 28, priority 31 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on US 41
Listed onlyUS 41/SR 54 West of Wilson Rd/SR 54 to East of Osprey Ln/ SR 54Construct grade separated interchange · FDOT · status as listed: ROW Advanced to FT27 from FY29MPO 2026 priority list, page 27, priority 1 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on Collier Pkwy
Listed onlyCollier Parkway/ SR 54 Interchange Collier Parkway at SR 54New interchange · FDOT · status as listed: Project Not in 2050 SIS CFPMPO 2026 priority list, page 28, priority 31 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on CR 52
Listed onlyFDOT phase: DesignCR 52/21st St/Suwanee Way/ Meridian Avenue Intersection Realignment Church Ave to Missouri Ave.Reconfigure intersection from T intersection to a 4-way intersection · Dade City Pasco County · status as listed: Design currently underway ROW funded FY 2026 Construction anticipated in 2027FDOT project page ↗MPO 2026 priority list, page 26, funded list, row 4 ↗
Listed onlyCR 52/Adair Rd/ Morningside Dr AdairRd/ Morningside Dr. to CR 52Roundabout or signalized intersection with added southbound turn lane · Pasco County · status as listed: Intersection Study completed in 2022MPO 2026 priority list, page 28, priority 26 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on CR 54
Listed onlyCR 54 (Wesley Chapel Blvd) N of Magnolia Blvd to N of Old Pasco RdAdd lanes and reconstruct (2U to 6D) · Pasco County · status as listed: CST UnderwayMPO 2026 priority list, page 26, funded list, row 1 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on CR 578 (County Line Rd)
Listed onlyCR 578/County Line Rd Mariner Blvd/ Shady Hills Rd to Suncoast PkwyWiden from 2 to 4 lanes · Pasco County Hernando County · status as listed: Under DesignMPO 2026 priority list, page 27, priority 8 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on Geiger Rd
Listed onlyGeiger Rd/US 301 Intersection Safety Improvement Geiger Rd and US 301 intersectionConstruct right turn lane onto US 301 from Geiger Rd · Pasco County · status as listed: No funds programmed in current CIPMPO 2026 priority list, page 28, priority 27 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on Grand Blvd
Listed onlyGrand Blvd Multi-Use Path North of Grand Blvd Bridge to Madison St and Main St.Multi-use path · City of New Port Richey · status as listed: Under DesignMPO 2026 priority list, page 28, priority 32 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on Old Dixie Hwy
Listed onlyOld Dixie Highway Mixed-Use Path Sea Ranch Dr to Aripeka RdRoadway Realignment and multi-use path · Pasco County · status as listed: Environmental Study UnderwayMPO 2026 priority list, page 27, priority 9 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Listed onlyOld Pasco Rd N of Overpass Rd to SR 52Widen from 2 to 4 lanes · Pasco County · status as listed: No funds programmed in current CIPMPO 2026 priority list, page 28, priority 22 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Listed onlyFDOT phase: DesignSR 52/Schrader Hwy E of Ehren Cutoff to Old Pasco RoadAdd lanes and reconstruct (2U to 4D West of Bellamy, 4D to 6D Bellamy to Old Pasco) · FDOT · status as listed: Under Design CST funded FY 2027FDOT project page ↗MPO 2026 priority list, page 26, funded list, row 11 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on US 19
Listed onlyUS 19 Pedestrian Crossings at Various Locations Various Locations to Various LocationsPedestrian signals, mid-block crossings, crosswalks · FDOT · status as listed: Design funded FY 2027 CST funded FY 2029MPO 2026 priority list, page 26, funded list, row 13 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Listed onlyFDOT phase: ConstructionIntersection Operational and Safety Improvement Intersection of Wire Road and US 301Install traffic and pedestrian signals, crosswalks, lighting, and other safety features · FDOT · status as listed: Under design CST funded FY 2025 and expected to begin in Early 2026FDOT project page ↗MPO 2026 priority list, page 26, funded list, row 14 ↗
Listed onlyGeiger Rd/US 301 Intersection Safety Improvement Geiger Rd and US 301 intersectionConstruct right turn lane onto US 301 from Geiger Rd · Pasco County · status as listed: No funds programmed in current CIPMPO 2026 priority list, page 28, priority 27 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Projects on Wire Rd
Listed onlyFDOT phase: ConstructionIntersection Operational and Safety Improvement Intersection of Wire Road and US 301Install traffic and pedestrian signals, crosswalks, lighting, and other safety features · FDOT · status as listed: Under design CST funded FY 2025 and expected to begin in Early 2026FDOT project page ↗MPO 2026 priority list, page 26, funded list, row 14 ↗
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Covered projects have their own guide, with every figure sourced and checked. Listed only projects are copied as written from an official list and linked to it; they aren’t checked or kept up to date here. Other Pasco road projects →
Stretch of road Rangeland Blvd corridor
Rangeland Blvd, Cattle Gap Trl to Bexley Village Dr (the new road, LRTP 114.2)
6 figures from 4 documents
Length of LRTP project 114.2, Rangeland Blvd, Cattle Gap Trl to Bexley Village DrPasco MPO 2050 Long Range Transportation Plan (with Appendix B project sheets and Appendix F socioeconomic forecast) · Verified by a human
Daily traffic (AADT), Rangeland Blvd, the new segment, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Travel lanes on the proposed Rangeland Blvd, both typical sections (two each way)Typical sections board · Verified by a human
Median width, standard typical section (Alternative A throughout)Typical sections board · Verified by a human
Median width, wider typical section (Alternatives D and E, South Branch Blvd to Bexley Village Dr)Typical sections board · Verified by a human
Design vehicle the proposed Rangeland Blvd is designed to accommodateCorrections and clarifications to this guide, by email · Verified by a human
Stretch of road Rangeland Blvd corridor
Rangeland Blvd, east of Gunn Hwy to Bexley Village Dr (the county capital plan's line)
6 figures from 1 document
County capital improvement plan, Rangeland Blvd (east of Gunn Hwy to Bexley Village Dr), FY 2026 (adopted)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Verified by a human
County capital improvement plan, Rangeland Blvd (east of Gunn Hwy to Bexley Village Dr), FY 2027 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Verified by a human
County capital improvement plan, Rangeland Blvd (east of Gunn Hwy to Bexley Village Dr), FY 2028 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Verified by a human
County capital improvement plan, Rangeland Blvd (east of Gunn Hwy to Bexley Village Dr), FY 2029 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Verified by a human
County capital improvement plan, Rangeland Blvd (east of Gunn Hwy to Bexley Village Dr), FY 2030 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Verified by a human
County capital improvement plan, Rangeland Blvd (east of Gunn Hwy to Bexley Village Dr), future years, after FY 2030Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Verified by a human
Intersection Rangeland Blvd corridor
Rangeland Blvd at Cattle Gap Trl
3 figures from 3 documents
Level of service, evening peak, Rangeland Blvd at Cattle Gap Trl, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, Rangeland Blvd at Cattle Gap Trl, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, Rangeland Blvd at Cattle Gap Trl, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Intersection Rangeland Blvd corridor
Rangeland Blvd at Gunn Hwy
3 figures from 3 documents
Level of service, evening peak, Rangeland Blvd at Gunn Hwy, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, Rangeland Blvd at Gunn Hwy, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, Rangeland Blvd at Gunn Hwy, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Bud Bexley Pkwy, Bexley Village Dr roundabout to Ballantrae Blvd
3 figures from 3 documents
Daily traffic (AADT), Bud Bexley Pkwy, Bexley Village Dr roundabout to Ballantrae Blvd, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bud Bexley Pkwy, Bexley Village Dr roundabout to Ballantrae Blvd, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bud Bexley Pkwy, Bexley Village Dr roundabout to Ballantrae Blvd, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Bud Bexley Pkwy, Bexley Village Dr to US 41 (LRTP 114.3)
1 figure from 1 document
Length of LRTP project 114.3, Bud Bexley Pkwy, Bexley Village Dr to US 41Pasco MPO 2050 Long Range Transportation Plan (with Appendix B project sheets and Appendix F socioeconomic forecast) · Verified by a human
Stretch of road Rangeland Blvd corridor
Caliente Blvd, US 41 to CR 583 (Ehren Cutoff) (LRTP 114.4)
1 figure from 1 document
Length of LRTP project 114.4, Caliente Blvd, US 41 to CR 583 (Ehren Cutoff)Pasco MPO 2050 Long Range Transportation Plan (with Appendix B project sheets and Appendix F socioeconomic forecast) · Verified by a human
Intersection Rangeland Blvd corridor
Bexley Village Dr roundabout (Bexley Village Dr at Bud Bexley Pkwy)
3 figures from 3 documents
Level of service, evening peak, Bexley Village Dr roundabout, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, Bexley Village Dr roundabout, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, Bexley Village Dr roundabout, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
A statement about this place: “Advancement of the Rangeland Boulevard interchange to the design and construction phases has been suspended until Pasco County demonstrates stakeholder support and confirms that the Bud Bexley Parkway and Bexley Village Drive intersection will operate acceptably with the interchange through the year 2050.” — Email on the Suncoast Parkway PD&E Study (FPID 448068-1) project status, in reply to a resident's inquiry
Intersection Rangeland Blvd corridor
Bud Bexley Pkwy at Ballantrae Blvd
3 figures from 3 documents
Level of service, evening peak, Bud Bexley Pkwy at Ballantrae Blvd, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, Bud Bexley Pkwy at Ballantrae Blvd, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, Bud Bexley Pkwy at Ballantrae Blvd, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Bexley Village Dr, just north of SR 54
3 figures from 3 documents
Daily traffic (AADT), Bexley Village Dr, toward SR 54, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bexley Village Dr, toward SR 54, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bexley Village Dr, toward SR 54, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Bexley Village Dr, just south of the roundabout
3 figures from 3 documents
Daily traffic (AADT), Bexley Village Dr, by the roundabout, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bexley Village Dr, by the roundabout, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bexley Village Dr, by the roundabout, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Bexley Village Dr, north leg (north-east of the roundabout)
3 figures from 3 documents
Daily traffic (AADT), Bexley Village Dr, north leg, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bexley Village Dr, north leg, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Bexley Village Dr, north leg, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Broad Porch Run, next to the roundabout
3 figures from 3 documents
Daily traffic (AADT), Broad Porch Run, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Broad Porch Run, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Broad Porch Run, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Ballantrae Blvd, just north of SR 54
3 figures from 3 documents
Daily traffic (AADT), Ballantrae Blvd, toward SR 54, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Ballantrae Blvd, toward SR 54, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Ballantrae Blvd, toward SR 54, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Ballantrae Blvd, just south of Bud Bexley Pkwy
3 figures from 3 documents
Daily traffic (AADT), Ballantrae Blvd, just south of Bud Bexley Pkwy, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Ballantrae Blvd, just south of Bud Bexley Pkwy, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Ballantrae Blvd, just south of Bud Bexley Pkwy, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
S Branch Blvd, between Rangeland Blvd and SR 54
2 figures from 2 documents
Daily traffic (AADT), S Branch Blvd, between Rangeland Blvd and SR 54, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), S Branch Blvd, between Rangeland Blvd and SR 54, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Gunn Hwy, south of SR 54
3 figures from 3 documents
Daily traffic (AADT), Gunn Hwy, south of SR 54, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), Gunn Hwy, south of SR 54, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), Gunn Hwy, south of SR 54, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
SR 54, the two segments labelled on the county's traffic boards
3 figures from 3 documents
Daily traffic (AADT), SR 54, the two segments the board labels, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Daily traffic (AADT), SR 54, the two segments the board labels, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Daily traffic (AADT), SR 54, the two segments the board labels, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
SR 54, Gunn Hwy to US 41 (FDOT's count sites)
1 figure from 1 document
Daily traffic (AADT), SR 54 between Gunn Hwy and US 41, FDOT's five count sites, 2025Portable traffic monitoring sites, 2025 annual average daily traffic (Transportation Data and Analytics) · Verified by a human
Stretch of road Rangeland Blvd corridor
SR 54, either side of the Suncoast Pkwy (the Turnpike's study)
1 figure from 1 document
Daily traffic (AADT), SR 54 either side of the Suncoast Pkwy, 2050 forecast in the Turnpike's widening study (parkway widened, no Rangeland Blvd interchange)Noise Study Report, Widening Suncoast Pkwy (SR 589) PD&E, Van Dyke Road to SR 52 · Verified by a human
Stretch of road Rangeland Blvd corridor
SR 54, the segment parallel to the Rangeland Blvd corridor (the county's letter)
1 figure from 1 document
Trucks as a share of daily traffic, the parallel segment of SR 54Corrections and clarifications to this guide, by email · Verified by a human
Intersection Rangeland Blvd corridor
SR 54 at Gunn Hwy
3 figures from 3 documents
Level of service, evening peak, SR 54 at Gunn Hwy, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Gunn Hwy, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Gunn Hwy, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Intersection Rangeland Blvd corridor
SR 54 at S Branch Blvd
3 figures from 3 documents
Level of service, evening peak, SR 54 at S Branch Blvd, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at S Branch Blvd, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at S Branch Blvd, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Intersection Rangeland Blvd corridor
SR 54 at the Suncoast Pkwy ramps, west
3 figures from 3 documents
Level of service, evening peak, SR 54 at Suncoast Pkwy ramps, west, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Suncoast Pkwy ramps, west, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Suncoast Pkwy ramps, west, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Intersection Rangeland Blvd corridor
SR 54 at the Suncoast Pkwy ramps, east
3 figures from 3 documents
Level of service, evening peak, SR 54 at Suncoast Pkwy ramps, east, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Suncoast Pkwy ramps, east, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Suncoast Pkwy ramps, east, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Intersection Rangeland Blvd corridor
SR 54 at Bexley Village Dr
3 figures from 3 documents
Level of service, evening peak, SR 54 at Bexley Village Dr, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Bexley Village Dr, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Bexley Village Dr, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Intersection Rangeland Blvd corridor
SR 54 at Ballantrae Blvd
3 figures from 3 documents
Level of service, evening peak, SR 54 at Ballantrae Blvd, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Ballantrae Blvd, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Ballantrae Blvd, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Intersection Rangeland Blvd corridor
SR 54 at Sunlake Blvd
3 figures from 3 documents
Level of service, evening peak, SR 54 at Sunlake Blvd, today (2023 counts)Existing traffic board (2023 counts), Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Sunlake Blvd, 2050 no-build2050 no-build traffic board, Public Workshop #3 · Verified by a human
Level of service, evening peak, SR 54 at Sunlake Blvd, 2050 build, Alternatives A, D and EPredicted traffic - Alternative A, D & E (2050 build board), Public Workshop #3 · Verified by a human
Stretch of road Rangeland Blvd corridor
Suncoast Pkwy, Hillsborough County line to SR 54 (FDOT's count site)
1 figure from 1 document
Daily traffic (AADT), Suncoast Pkwy between the Hillsborough County line and SR 54, FDOT count, 2025Portable traffic monitoring sites, 2025 annual average daily traffic (Transportation Data and Analytics) · Verified by a human
Stretch of road Rangeland Blvd corridor
Suncoast Pkwy, W Lutz Lake Fern Rd to SR 54 (the Turnpike's study)
1 figure from 1 document
Daily traffic (AADT), Suncoast Pkwy between W Lutz Lake Fern Rd and SR 54, 2050 forecast in the Turnpike's widening study (parkway widened, no Rangeland Blvd interchange)Noise Study Report, Widening Suncoast Pkwy (SR 589) PD&E, Van Dyke Road to SR 52 · Verified by a human
Stretch of road Rangeland Blvd corridor
Suncoast Pkwy, SR 54 to Ridge Rd
2 figures from 2 documents
Daily traffic (AADT), Suncoast Pkwy between SR 54 and Ridge Rd, FDOT count, 2025Portable traffic monitoring sites, 2025 annual average daily traffic (Transportation Data and Analytics) · Verified by a human
Daily traffic (AADT), Suncoast Pkwy between SR 54 and Ridge Rd, 2050 forecast in the Turnpike's widening study (parkway widened, no Rangeland Blvd interchange)Noise Study Report, Widening Suncoast Pkwy (SR 589) PD&E, Van Dyke Road to SR 52 · Verified by a human
Stretch of road Rangeland Blvd corridor
US 41, SR 54 to Sundance Lake Blvd (FDOT's count sites)
1 figure from 1 document
Daily traffic (AADT), US 41 between SR 54 and Sundance Lake Blvd, FDOT's four count sites, 2025Portable traffic monitoring sites, 2025 annual average daily traffic (Transportation Data and Analytics) · Verified by a human
Stretch of road Sunlake Blvd corridor
Sunlake Blvd, Center Village Dr to south of Appenzeller Blvd (the design project)
7 figures from 1 document
Approximate length of the Sunlake Blvd design project, Center Village Dr to south of Appenzeller BlvdRequest for Statement of Qualifications RSQ-BW-26-019: Design of Sunlake Boulevard from Center Village Drive to South of Appenzeller Boulevard · Verified by a human
Right-of-way the Bexley North MPUD (rezoning no. 7242) will dedicate for the Sunlake Blvd extensionRequest for Statement of Qualifications RSQ-BW-26-019: Design of Sunlake Boulevard from Center Village Drive to South of Appenzeller Boulevard · Verified by a human
Travel lanes in the ultimate configuration of the Sunlake Blvd extension (11-foot lanes)Request for Statement of Qualifications RSQ-BW-26-019: Design of Sunlake Boulevard from Center Village Drive to South of Appenzeller Boulevard · Checked by AI
11-foot lanes in the interim configuration of the Sunlake Blvd extensionRequest for Statement of Qualifications RSQ-BW-26-019: Design of Sunlake Boulevard from Center Village Drive to South of Appenzeller Boulevard · Checked by AI
Road type named on the ultimate-condition typical section of the Sunlake Blvd extensionRequest for Statement of Qualifications RSQ-BW-26-019: Design of Sunlake Boulevard from Center Village Drive to South of Appenzeller Boulevard · Checked by AI
Design speed on the typical sections of the Sunlake Blvd extensionRequest for Statement of Qualifications RSQ-BW-26-019: Design of Sunlake Boulevard from Center Village Drive to South of Appenzeller Boulevard · Verified by a human
Posted speed on the typical sections of the Sunlake Blvd extensionRequest for Statement of Qualifications RSQ-BW-26-019: Design of Sunlake Boulevard from Center Village Drive to South of Appenzeller Boulevard · Verified by a human
Stretch of road Sunlake Blvd corridor
Sunlake Blvd, north of Bud Bexley Pkwy to south of the Angeline line (capital plan line)
6 figures from 1 document
County capital improvement plan, Sunlake Blvd (north of Bud Bexley Pkwy to south of the Angeline line), FY 2026 (adopted)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI
County capital improvement plan, Sunlake Blvd (north of Bud Bexley Pkwy to south of the Angeline line), FY 2027 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI
County capital improvement plan, Sunlake Blvd (north of Bud Bexley Pkwy to south of the Angeline line), FY 2028 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI
County capital improvement plan, Sunlake Blvd (north of Bud Bexley Pkwy to south of the Angeline line), FY 2029 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI
County capital improvement plan, Sunlake Blvd (north of Bud Bexley Pkwy to south of the Angeline line), FY 2030 (proposed)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI
County capital improvement plan, Sunlake Blvd (north of Bud Bexley Pkwy to south of the Angeline line), future years, after FY 2030Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI
Stretch of road Sunlake Blvd corridor
Sunlake Blvd, south of the Angeline line to south of Wilton Way (capital plan line)
1 figure from 1 document
County capital improvement plan, Sunlake Blvd (south of the Angeline line to south of Wilton Way), FY 2026 (adopted)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI
Stretch of road Sunlake Blvd corridor
Sunlake Blvd, south of Wilton Way to Anchor Dune Dr (capital plan line)
1 figure from 1 document
County capital improvement plan, Sunlake Blvd (south of Wilton Way to Anchor Dune Dr), FY 2026 (adopted)Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan) · Checked by AI