What has happened on each project, and what the county’s plans say comes next. Every entry names the document it comes from. Every project gets the same kinds of entry — each workshop, Commission action, contract, change order, plan document and deadline — not just the notable ones. Tap an entry for details.
No entries match.
What the county’s plans say will happen. These are plans, not events: they can change in any budget cycle.
Center Village Dr to south of the Angeline line
Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)
Rangeland route study
The schedule board notes the schedule is subject to change and construction is "TBD".
Center Village Dr to south of the Angeline line
Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)
Center Village Dr to south of the Angeline line
Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)
Rangeland route study
Source: Public Workshop #3 newsletter
Rangeland route study
Under Miscellaneous Business the minutes record, for Commissioner Starkey (District 3): "She displayed pictures and spoke regarding the Rangeland Boulevard workshop, Staff, questions, and a video." For Commissioner Yeager (District 4): "She displayed pictures and spoke regarding the Rangeland Boulevard study, the set-up, the turnout, and citizen votes." The minutes record no vote on either.
Rangeland route study
The newsletter said materials would be online the same day.
7 figures changed from the earlier documents →
Source: Public Workshop #3 newsletter
Rangeland route study
The minutes list the topics of twelve public speakers together, without saying who raised which. The run that includes Rangeland reads: "legal and financial liabilities with Rangeland Boulevard; a federal complaint that was filed; the State inspection; the Rangeland Boulevard project; the Bexley community". These are speakers' topics as the clerk summarized them; the minutes do not say how they relate to one another, and this site has not checked them. Directly after the list the minutes record: "Discussion was held regarding direction to Staff and a future meeting on Rangeland." No date is given.
See the corrections at the foot of the guide.
Source: Corrections and clarifications to this guide, by email
Orange Belt Trail PD&E study (US 41 and Caliente Blvd to Dade City)
The minutes, published 6 October 2026, record "Approved Staff's recommendation." The alternatives are named in the resolution on the meeting agenda; the minutes do not repeat them.
The agenda memorandum recommends the Board "Approve the 2026 TRIP List Project Priorities." The attached District 7 list shows Rangeland Blvd from Cattle Gap Trail to Bexley Village Dr (requested phases PE, ROW, CST) at rank 4, and Sunlake Blvd from Center Village Dr to south of Appenzeller Blvd (requested phase CST) at rank 5. The list's cover reads "Adoption date: September 01, 2026". Minutes of this meeting have not been found on the county's agenda portal, so this site does not record what the Board did.
Orange Belt Trail PD&E study (US 41 and Caliente Blvd to Dade City)
The minutes (printed in the 30 September packet) record a unanimous voice vote "to recommend approval of the TRIP 2026 project priority list as it relates to Pasco County, for advancement to the MPO Board." TRIP is the state's Transportation Regional Incentive Program.
The minutes (printed in the 30 September packet) record a motion to approve that "passed unanimously by voice vote."
Bud Bexley Pkwy extension (contract name "Tower Road Route Study")
Adds 90 days to finalize the route study and pond siting report. No change in fee. Reported as a Noted Item. Change orders 1 and 2, and the original award, were not found on the county's agenda portal.
Both listed under "Construction unfunded". Rangeland's request is a TRIP grant for right-of-way, design and construction.
Figures from this: Funded phase and year for Sunlake Blvd (454568-1) in the MPO 2026 List of Project Priorities (Route study, FY 2026)
Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)
Center Village Dr to south of Appenzeller Blvd
Rangeland route study (contract name "Tower Road PD&E Study")
The presentation of the study's recommendations to the Commission, set for 17 Feb 2026, was moved to 24 Mar 2026 "to ensure the attendance of all commissioners." No change in fee. Reported as a Noted Item.
Bud Bexley Pkwy extension (contract name "Tower Road Route Study")
Adds 120 days to finalize the route study and pond siting report. No change in fee. Reported as a Noted Item.
Center Village Dr to south of Appenzeller Blvd
Center Village Dr to south of Appenzeller Blvd
Rangeland route study (contract name "Tower Road PD&E Study")
Adds 120 days to formulate the recommendations and present them to the Commission. No change in fee. Reported as a Noted Item.
Center Village Dr to south of Appenzeller Blvd
Figures from this: Approximate length of the Sunlake Blvd design project, Center Village Dr to south of Appenzeller Blvd (2.70 miles); Right-of-way the Bexley North MPUD (rezoning no. 7242) will dedicate for the Sunlake Blvd extension (166 feet)
Bud Bexley Pkwy extension (contract name "Tower Road Route Study")
Adds 90 days for survey delays and for developing and evaluating additional conceptual design alternatives. No change in fee. Reported as a Noted Item.
Includes year-by-year lines for Rangeland Blvd and for three pieces of Sunlake Blvd. Only the first year is appropriated.
Figures from this: County capital improvement plan, Rangeland Blvd (east of Gunn Hwy to Bexley Village Dr), FY 2026 (adopted) ($6.0M); County capital improvement plan, Sunlake Blvd (north of Bud Bexley Pkwy to south of the Angeline line), FY 2026 (adopted) ($4.2M)
Source: Fiscal Year 2026 Adopted Budget (includes the FY 2026-2030 Capital Improvement Plan)
Rangeland route study (contract name "Tower Road PD&E Study")
Adds 60 days to formulate the study's recommendations and present them to the Commission. No change in fee. Reported as a Noted Item.
Bud Bexley Pkwy extension (contract name "Tower Road Route Study")
Adds 180 days to overcome survey delays from Hurricanes Helene and Milton. No change in fee. Reported as a Noted Item.
Rangeland route study
Rangeland route study (contract name "Tower Road PD&E Study")
Reasons given: coordination with FDOT as lead agency for the Federal Highway Administration on the NEPA and PD&E process; coordination with Florida's Turnpike on its Suncoast Parkway study, including a possible Rangeland interchange; and the workshop cancelled by Hurricane Helene. Reported as a Noted Item.
Rangeland route study
Rangeland route study
Rangeland route study
Announced in the county's September 2024 newsletter, with comments open to 16 October 2024. Kisinger Campo's change order 1 records the cancellation and the new date, 30 January 2025.
Bud Bexley Pkwy extension (contract name "Tower Road Route Study"), west of Sunlake Blvd to east of US 41
Adds 230 days and $304,071 for topographic survey and mapping.
Rangeland route study
Rangeland route study (contract name "Tower Road PD&E Study")
Not to exceed $1,864,209.