Timeline

What has happened on each project, and what the county’s plans say comes next. Every entry names the document it comes from. Every project gets the same kinds of entry — each workshop, Commission action, contract, change order, plan document and deadline — not just the notable ones. Tap an entry for details.

Planned

What the county’s plans say will happen. These are plans, not events: they can change in any budget cycle.

  1. FY 2029 Planned Rangeland Blvd Construction funded in the county capital plan
  2. FY 2028-2029 Planned Sunlake Blvd Construction funded in the county capital plan

    Center Village Dr to south of the Angeline line

    Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)

  3. Fall 2026 Planned Rangeland Blvd Study complete (anticipated)

    Rangeland route study

    The schedule board notes the schedule is subject to change and construction is "TBD".

    Source: Project schedule board, Public Workshop #3

  4. FY 2027 Planned Rangeland Blvd Right-of-way funded in the county capital plan
  5. FY 2027 Planned Sunlake Blvd Right-of-way funded in the county capital plan

    Center Village Dr to south of the Angeline line

    Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)

  6. FY 2026 Planned Rangeland Blvd Design funded in the county capital plan
  7. FY 2026 Planned Sunlake Blvd Design funded in the county capital plan

    Center Village Dr to south of the Angeline line

    Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)

Coming up

  1. 8 Oct 2026 Deadline Rangeland Blvd Workshop 3 comments due: received, or postmarked if mailed, to be in the workshop record

    Rangeland route study

    Source: Public Workshop #3 newsletter

What has happened

  1. 24 Sep 2026 Meeting Rangeland Blvd Public Workshop 3: Alternatives A, D and E, with new traffic boards and matrix

    Rangeland route study

    The newsletter said materials would be online the same day.

    7 figures changed from the earlier documents →

    Source: Public Workshop #3 newsletter

  2. 14 Sep 2026 Document Rangeland Blvd County Transportation Engineering sends corrections to this guide

    See the corrections at the foot of the guide.

    Source: Corrections and clarifications to this guide, by email

  3. 9 Sep 2026 Meeting Rangeland Blvd Orange Belt Trail study on the Commission agenda, with a resolution approving alternatives 1, 2A, 3A, 4A and 5A

    Orange Belt Trail PD&E study (US 41 and Caliente Blvd to Dade City)

    The minutes of this meeting were not yet published on 28 September 2026, so the outcome is not recorded here.

    Figures from this: Orange Belt Trail PD&E study (US 41 and Caliente Blvd to Meridian Ave and 8th St, Dade City) on the Board of County Commissioners agenda, with a resolution to approve recommended alternatives 1, 2A, 3A, 4A and 5A (9 Sep 2026)

    Source: Board of County Commissioners meeting agenda, 9 September 2026

  4. 11 Aug 2026 Decision Rangeland Blvd Commission continues the Orange Belt Trail study item to 9 September
  5. 14 Jul 2026 Change order Rangeland Blvd Change order 7: completion extendedCompletion moved from19 Jun 2026 to 17 Sep 2026

    Bud Bexley Pkwy extension (contract name "Tower Road Route Study")

    Adds 90 days to finalize the route study and pond siting report. No change in fee. Reported as a Noted Item. Change orders 1 and 2, and the original award, were not found on the county's agenda portal.

    Source: Board of County Commissioners meeting, 14 July 2026: Change Order No. 7, Consor North America (Tower Road / Bud Bexley Parkway Extension route study)

  6. 11 Jun 2026 Document Rangeland Blvd Sunlake Blvd MPO 2026 List of Project Priorities: Rangeland Blvd at no. 10, Sunlake Blvd at no. 11

    Both listed under "Construction unfunded". Rangeland's request is a TRIP grant for right-of-way, design and construction.

    Figures from this: Funded phase and year for Sunlake Blvd (454568-1) in the MPO 2026 List of Project Priorities (Route study, FY 2026)

    Source: Pasco MPO 2026 Multimodal Transportation List of Project Priorities (LOPP)

  7. 2 Jun 2026 Decision Sunlake Blvd Commission approves the design shortlist (WGI, Burgess & Niple, IC&E) and delegates the contract to the County Administrator
  8. 7 Apr 2026 Change order Rangeland Blvd Change order 4: completion extendedCompletion moved from2 Mar 2026 to 1 May 2026

    Rangeland route study (contract name "Tower Road PD&E Study")

    The presentation of the study's recommendations to the Commission, set for 17 Feb 2026, was moved to 24 Mar 2026 "to ensure the attendance of all commissioners." No change in fee. Reported as a Noted Item.

    Source: Board of County Commissioners meeting, 7 April 2026: Change Order No. 4, Kisinger Campo & Associates, and No. 6, Consor North America

  9. 7 Apr 2026 Change order Rangeland Blvd Change order 6: completion extendedCompletion moved from19 Feb 2026 to 19 Jun 2026

    Bud Bexley Pkwy extension (contract name "Tower Road Route Study")

    Adds 120 days to finalize the route study and pond siting report. No change in fee. Reported as a Noted Item.

    Source: Board of County Commissioners meeting, 7 April 2026: Change Order No. 4, Kisinger Campo & Associates, and No. 6, Consor North America

  10. 31 Mar 2026 Meeting Sunlake Blvd Evaluation committee ranks the design firms at a public meeting
  11. 3 Feb 2026 Milestone Sunlake Blvd Design proposals opened: five firms responded
  12. 6 Jan 2026 Change order Rangeland Blvd Change order 3: completion extendedCompletion moved from2 Nov 2025 to 2 Mar 2026

    Rangeland route study (contract name "Tower Road PD&E Study")

    Adds 120 days to formulate the recommendations and present them to the Commission. No change in fee. Reported as a Noted Item.

    Source: Board of County Commissioners meeting, 6 January 2026: Change Order No. 3, Kisinger Campo & Associates (Tower Road PD&E Study)

  13. 18 Dec 2025 Contract Sunlake Blvd County asks for design firms: solicitation RSQ-BW-26-019 issued
  14. 9 Dec 2025 Change order Rangeland Blvd Change order 5: completion extendedCompletion moved from21 Nov 2025 to 19 Feb 2026

    Bud Bexley Pkwy extension (contract name "Tower Road Route Study")

    Adds 90 days for survey delays and for developing and evaluating additional conceptual design alternatives. No change in fee. Reported as a Noted Item.

    Source: Board of County Commissioners meeting, 9 December 2025: Change Order No. 5, Consor North America (Tower Road route study)

  15. 16 Sep 2025 Decision Rangeland Blvd Sunlake Blvd Commission adopts the FY 2026 budget, with the FY 2026-2030 capital improvement plan
  16. 19 Aug 2025 Change order Rangeland Blvd Change order 2: completion extendedCompletion now 2 Nov 2025

    Rangeland route study (contract name "Tower Road PD&E Study")

    Adds 60 days to formulate the study's recommendations and present them to the Commission. No change in fee. Reported as a Noted Item.

    Source: Board of County Commissioners meeting, 19 August 2025: Change Order No. 2, Kisinger Campo & Associates (Tower Road PD&E Study)

  17. 3 Jun 2025 Change order Rangeland Blvd Change order 4: completion extendedCompletion moved from25 May 2025 to 21 Nov 2025

    Bud Bexley Pkwy extension (contract name "Tower Road Route Study")

    Adds 180 days to overcome survey delays from Hurricanes Helene and Milton. No change in fee. Reported as a Noted Item.

    Source: Board of County Commissioners meeting, 3 June 2025: Change Order No. 4, Consor North America (Tower Road route study)

  18. 1 May 2025 Meeting Rangeland Blvd Public Workshop 2

    Rangeland route study

    Source: Project schedule board, Public Workshop #3

  19. 22 Apr 2025 Change order Rangeland Blvd Change order 1: completion extendedCompletion moved from7 Mar 2025 to 3 Sep 2025

    Rangeland route study (contract name "Tower Road PD&E Study")

    Reasons given: coordination with FDOT as lead agency for the Federal Highway Administration on the NEPA and PD&E process; coordination with Florida's Turnpike on its Suncoast Parkway study, including a possible Rangeland interchange; and the workshop cancelled by Hurricane Helene. Reported as a Noted Item.

    Source: Board of County Commissioners meeting, 22 April 2025: Change Order No. 1, Kisinger Campo & Associates (Tower Road PD&E Study)

  20. 30 Jan 2025 Meeting Rangeland Blvd Public Workshop 1

    Rangeland route study

    Source: Project schedule board, Public Workshop #3

  21. 18 Jan 2025 Document Rangeland Blvd Alternatives evaluation matrix (Build A and Build B)

    Rangeland route study

    Source: Rangeland Blvd alternatives evaluation matrix

  22. 25 Sep 2024 Meeting Rangeland Blvd Public workshop scheduled for this date cancelled because of Hurricane Helene

    Rangeland route study

    Announced in the county's September 2024 newsletter, with comments open to 16 October 2024. Kisinger Campo's change order 1 records the cancellation and the new date, 30 January 2025.

    Source: Board of County Commissioners meeting, 22 April 2025: Change Order No. 1, Kisinger Campo & Associates (Tower Road PD&E Study)

  23. 17 Sep 2024 Change order Rangeland Blvd Change order 3: completion extendedCompletion moved from8 Oct 2024 to 25 May 2025

    Bud Bexley Pkwy extension (contract name "Tower Road Route Study"), west of Sunlake Blvd to east of US 41

    Adds 230 days and $304,071 for topographic survey and mapping.

    Source: Board of County Commissioners meeting, 17 September 2024: Change Order No. 3, Consor Engineers (Tower Road route study)

  24. 13 Mar 2023 Milestone Rangeland Blvd Study began

    Rangeland route study

    Source: Project schedule board, Public Workshop #3

  25. 7 Mar 2023 Contract Rangeland Blvd Study contract awarded to Kisinger Campo & Associates, eastern end of Rangeland Blvd to Bexley Village Dr